Hold Cleaning Standards: Hospital, Grain and Normal Clean

Hospital, grain, normal and shovel clean: the four hold cleaning standards compared, what each demands, the cargoes it suits and how holds pass.

このレポートは英語で公開されています。翻訳は近日公開予定です。

公開日
読了時間
6分
著者
CARGOWARD® Technical Desk · Hold Cleaning
サービスライン
船倉清掃 →
共有

CW-DWG-201 · 船倉断面

Hold cleaning standards are the shorthand the dry bulk trade uses for how clean a cargo hold must be before the next cargo goes in. "Grain clean" in a fixture or voyage instruction sets a precise expectation for owners, charterers, shippers and the surveyor who will inspect the holds — and a hold that misses it can mean a failed inspection, a notice of readiness that does not stand, and time lost at the berth.

The four hold cleaning standards

The terms are trade practice rather than definitions in a convention, and clubs and charterers word them slightly differently. The core of each is stable:

StandardWhat the hold must beTypical next cargoWashing
Hospital cleanSpotless and dry; no residues, no loose scale; paint intact and free of rust stainingKaolin, rice, some food-grade and sensitive cargoesFull wash, often chemical, fresh-water rinse, drying; sometimes touch-up painting
Grain cleanClean and dry; free of residues of the previous cargo, insects, odour, loose rust scale and paint flakesGrain, soybeans, sugar, fertilisers, cementSweep, salt-water wash, chemical where needed, fresh-water rinse, drying
Normal cleanSwept and washed; residues of the previous cargo removedA cargo similar or compatible with the last oneSweep and salt-water wash, sometimes a rinse
Shovel cleanResidues a shovel or grab can reach removed; no washing requiredThe same cargo, or a compatible lower-grade oneNone: sweeping and removal only

"Grain clean" is the workhorse. It is what most grain, fertiliser and cement charters ask for, and what most hold inspections in Brazil's grain ports test against.

Which standard the next cargo needs

Start from the next cargo and the documents. The charter party, the voyage instructions and the shipper's requirements say which standard applies; some cargoes add their own conditions in the IMSBC Code or in the shipper's declaration. When the wording is vague, agree the standard in writing before the ship arrives.

Then look at the previous cargo. It decides how much work the standard takes:

Previous cargoNext cargoStandardWhat makes it hard
CoalGrainGrain cleanCoal dust bonds to paint: chemical wash, then fresh-water rinse
Petroleum cokeSoybeansGrain cleanOily, sticky residue and strong odour
Iron oreCoalNormal cleanHeavy residues in corners and under the hatch coamings
Fertiliser (urea)SugarGrain cleanResidues absorb moisture and corrode: thorough rinse and drying
GrainGrainNormal or grain cleanInsects and odour; usually sweeping and a wash

The hold cleaning planner sets out this matrix for every pairing: the standard, the method, the hours and the water per hold, and the risk at inspection.

The washing sequence

A cleaning that passes on the first inspection follows the same order every time, from the top of the hold down and from dry work to wet:

  1. Sweep and remove the residues

    Sweep tank top, hopper sides and frames; clear the residues from under the hatch coamings and the top of the frames. Land the swept residue ashore or treat it as the rules require — it is cargo residue under MARPOL Annex V.

  2. Wash with salt water

    High-pressure washing from the top down: hatch covers and coamings, topside tanks, frames, hopper sides, tank top. Pressure and the angle of the jet matter more than water volume.

  3. Apply chemicals where needed

    For coal, petcoke or oily residues, apply a cleaning chemical approved for the purpose, respect its dwell time, and wash it off before it dries.

  4. Rinse with fresh water

    Salt left on steel corrodes it and contaminates sensitive cargoes. A fresh-water rinse removes chlorides; some charterers test for them.

  5. Dry, ventilate and finish

    Pump out and clean the bilge wells, ventilate until the steel is dry, then check that bilge covers are sealed and hatch covers close weathertight.

Why fresh water after salt water?

Salt water does most of the cleaning, but every litre leaves salt behind as it dries. Chloride residues corrode the steel under the paint, and some cargoes — fertilisers, grain bound for sensitive markets, kaolin — are contaminated by them. A final fresh-water rinse takes the chlorides off; where the charter or the shipper asks for it, a silver-nitrate test on the bulkheads shows whether any remain.

Time and water per hold

The figures below are an illustrative estimate for one Supramax hold going from coal to grain clean, with five high-pressure jets working. Every hold, coating and residue differs; the point is the shape of the calculation.

—セルを指すと数式が表示されます
One hold, coal to grain clean
ItemValueUnit
Surface to wash3,000m²
Jets working5jets
Washing rate per jet120m²/h
Washing passes (salt water, fresh-water rinse)2passes
Chemical application and dwell2h
Drying and ventilation6h
Washing time10h
Flow per jet20l/min
Water used60m³
Hold ready for inspection18h
One hold, coal to grain clean
Illustrative figures for one hold; the planner works the whole ship against the time in port.

Two things stand out. Washing time scales with the surface, not the cargo tonnage; and drying is a fixed cost that no number of jets shortens. When the stay in port is short, the order in which holds are cleaned — and whether cleaning starts at sea, on the ballast passage — matters as much as the crew size.

How holds are inspected

At inspection a surveyor, often appointed by the shippers or charterers, walks every hold. Most inspections in grain ports cover the same ground:

  • No residues of the previous cargo anywhere, including the underside of hatch covers and the top of the frames
  • No loose rust scale or paint flakes that could fall into the cargo
  • No odour of the previous cargo
  • Holds dry; no standing water in the bilges
  • Bilge wells clean, strainers in place, covers sealed with burlap where required
  • No insects or infestation
  • Hatch covers closing weathertight, rubber seals in good condition
  • No chloride residues where the cargo requires a test

The test that settles most arguments is simple: a white cloth wiped along the steel. If it comes away marked with the previous cargo, the hold fails.

Hold washing water is itself regulated: where it may be discharged, and what must be kept on board, depends on whether the cargo residues it carries are harmful to the marine environment. See MARPOL Annex V and hold washing water.

Questions about hold cleaning standards

Who decides that a hold is grain clean?

The surveyor appointed under the charter party or by the shippers inspects the holds and passes or fails them. The standard itself comes from the charter or the voyage instructions.

Can the crew clean to hospital standard at sea?

Sometimes, if the passage is long enough and the coating is in good condition. Hospital clean often needs paint touch-ups and full drying, which is easier with a shore team in port or at anchor.

Is shovel clean ever enough?

Yes, when the next cargo is the same or compatible and the charter allows it. It means residues are removed; it does not include washing.

For a cargo change in a Brazilian port, the desk's cargo hold cleaning teams work to the standard the charter names and stay for the inspection.

出典

  1. Cargo Hold Cleaning Standards GuidanceBritannia P&I Club · 2024
  2. Hold cleanlinessThe Shipowners' Club
  3. Hold cleaning of bulk vesselsThe Swedish Club
  4. Carefully to Carry: hold cleaningUK P&I Club · 2023

実務で活用する

T-01船倉清掃プランナー積荷切替の清掃基準、在港期間に対する停泊期間、検査リスク、方法ツールを開く

SVC-01 · サービス

船倉清掃

船倉と燃料タンクの清掃を、バース枠に合わせて船倉ごとに計画し、残渣ごとの扱いを知るクルーが施工します。最後は、サーベイヤーと傭船者が確認できる写真と廃棄物記録で締めくくります。

メールでレポートを受け取る

新しいレポートを、受信トレイへ。

デスクからの方法、数値、エビデンス。レポートが公開されたときに、お使いの言語でメールを1通。それ以外は送りません。

レポートが公開されるたびにメールを1通お送りします(送信するリンクで確認後)。配信停止はいつでも可能です。 プライバシーポリシー

オペレーションデスク · 24/7

業務サポートをご依頼ください。 デスクは24時間対応です。

船名、港、ETAをお知らせください。コールセンターではなくコーディネーターが、昼夜を問わず15分以内に返信します。

計画を依頼