01At a glance
Rio de Janeiro at a glance
Ships enter by the Cotunduba channel, with a draft of up to 15.85 m, and berth at the Commercial Quay (Gamboa and São Cristóvão) or at the TECON-RJ container terminals, where the channel takes 14.50 m, 15.30 m with tide, for ships up to 349 m long.
The Navy's 2026 predictions for Porto do Rio de Janeiro, Ilha Fiscal give a mean tidal range of 0.71 m, with mean sea level 0.73 m above chart datum. In INMET's 1961–1990 normals for Rio de Janeiro, rain totals 1,173 mm a year; December is the wettest month and August the driest.
PortosRio publishes the draft of every berth in its normative instruction 14.001.08. The table on this page is version 8.0, in force since 10 April 2026, quay by quay, with the bollards each berth spans.
- Region
- Southeast · RJ
- Position
- 22°53′S 043°11′W
- From the desk in Santos
- 185 NM · 070°
- Figures read
- Nov 18, 2026 · 3 sources
- Tide station
- Porto do Rio de Janeiro, Ilha Fiscal · 1.6 km
- Climate station
- Rio de Janeiro · 1961–1990
- Terminals attended
- Niterói
02Access and limits
What the channel and the berths take.
The figures the port authority and the Harbour Master publish, each with its source. Drafts in metres, referred to chart datum.
- Channel maximum operating draft
- 15.85 m[1]
Cotunduba channel (Canal Varrido), the entrance to Guanabara Bay
- Channel draft, without / with tide
- 14.50 / 15.30 m[1]
TECON-RJ channel and turning basin, ships up to 349 m long
- Deepest berth draft
- 15.30 m[1]
TECON 1, 2, 3 and the extension, subject to the ramp-up
- Longest ship accepted
- 349 m[1]
TECON-RJ, beam up to 52 m
- Berths
- 41[1]
Berths and berth sections in the PortosRio table
- 01Container ships up to 12.60 m draft, with the sea at Beaufort 1 or less, and other ships up to 11.50 m may enter by the Santa Cruz channel (Barra Grande), day or night.[1]
- 02The access channel, from buoys 1 and 2 between the Navy Arsenal and Ilha das Enxadas, is one-way; it splits at Ilha das Enxadas into the Commercial Quay channel and the TECON-RJ channel, which has priority.[1]
- 03Commercial Quay channel: 10.30 m between bollards 36 and 110 (up to 11.00 m with 0.70 m of flood tide), 9.00 m between 110 and 129 (9.70 m) and 8.50 m between 129 and 205 (9.00 m).[1]
- 04Between bollards 36 and 129, a ship leaving may add up to 0.70 m of flood tide to the berth draft, never above the draft of its channel.[1]
- 05TECON-RJ berthing and unberthing take as reference wind up to 15 knots, gusts aside, and visibility of at least 2 nautical miles.[1]
- 06The 15.30 m drafts at TECON 1, 2, 3 and the extension depend on the ramp-up of larger ships the Capitania dos Portos do Rio de Janeiro approves.[1]
03Berths
Berth by berth.
As the port authority or the Harbour Master publishes them, berth by berth, in metres. Type a draft to see which berths take it.
| Berth | |
|---|---|
| Quadro de Boias de Manguinhos | |
| 2NRF Quadro de Boias de Manguinhos | 11.47 |
| Cais da Gamboa, cabeços 36 a 162 | |
| 2N01 ESMAPA, parte 1 (36–38) | — |
| 2N01 ESMAPA, parte 2 (38–43) | 5.30 |
| 2N02 Terminal de Passageiros 1 (43–53) | 8.90 |
| 2N03 Terminal de Passageiros 2 (53–62) | 8.90 |
| 2N04 Armazém 4 (62–70) | 8.90 |
| 2N04 Armazém 5 (70–73) | 9.50 |
| 2N05 Armazém 6, parte 1 (73–77) | 9.50 |
| 2N05 Armazém 6, parte 2 (77–79) | 9.60 |
| 2N06 Armazém 7, parte 1 (79–81) | 7.30 |
| 2N06 Armazém 7, parte 2 (81–86) | 8.20 |
| 2N06 Armazém 8 (86–90) | 9.00 |
| 2N07 Pátio 8/9 (90–100) | 10.50 |
| 2N08 Pátio 9 (100–110) | 10.50 |
| 2N09 Armazém 10 (110–116) | 9.50 |
| 2N10 Terminal de Trigo (116–124A) | 9.10 |
| 2N11 Armazém 13, parte 1 (125–129) | 9.10 |
| 2N11 Armazém 13, parte 2 (129–134) | 6.90 |
| 2P14 Terminal Petrobras, Armazém 14 (134–139) | 6.80 |
| 2P15 Terminal Petrobras, Armazém 15 (139–146) | 6.90 |
| 2N16 Armazém 16 (146–152) | 5.00 |
| Berth | |
|---|---|
| Cais da Gamboa, cabeços 36 a 162 | |
| 2N17 Armazém 17 (152–157) | 3.30 |
| 2N18 Armazém 18 (157–162) | 2.90 |
| Cais de São Cristóvão, cabeços 166 a 216 | |
| 2PAL Terminal Petrobras AL, parte 1 (166–170) | 3.90 |
| 2PAL Terminal Petrobras AL, parte 2 (170–175) | 6.00 |
| 2PAL Terminal Petrobras AL, parte 3 (175–178) | 5.80 |
| 2P19 Terminal Petrobras SC, parte 1 (178–180) | 5.80 |
| 2P19 Terminal Petrobras SC, parte 2 (180–190) | 8.10 |
| 2TS1 Terminal Siderúrgico, parte 1 (190–197) | 8.60 |
| 2NTO Terminal de Óleo (197–205) | 8.50 |
| 2TS2 Terminal Siderúrgico, parte 2 (205–209) | 8.60 |
| 2TS2 Terminal Siderúrgico, parte 3 (209–212) | 9.00 |
| 2TS2 Terminal Siderúrgico, parte 4 (212–214) | 9.00 |
| 2TS2 Terminal Siderúrgico, parte 5 (214–215) | 8.60 |
| 2TS2 Terminal Siderúrgico, parte 6 (215–216) | 4.30 |
| TECON-RJ | |
| 2R11 TECON 5, MCAR (DMC1–237) | 12.20 |
| 2R12 TECON 4, MCAR (237–244) | 12.50 |
| 2C21 TECON 3, MRIO (244–260) | 15.30 |
| 2C22 TECON 2, MRIO (260–277) | 15.30 |
| 2C11 TECON 1, ICTSI (277–290) | 15.30 |
| 2C12 TECON Prolongamento, ICTSI (290–309) | 15.30 |
Source [1] · The check compares with the published maximum drafts only; under-keel clearance, trim and the day’s tide stay with the desk and the pilots.
04Tides
The tide, level by level.
At the Navy tide station Porto do Rio de Janeiro, Ilha Fiscal, 1.6 km from the port reference, from the 2026 predictions. Heights in metres above chart datum.
Heights above chart datum
- Highest predicted
- 1.49 m
- Mean high water
- 1.10 m
- Mean sea level
- 0.73 m
- Mean low water
- 0.39 m
- Chart datum
- 0.00 m
- Lowest predicted
- -0.13 m
Means and extremes computed from the 1,546 high and low waters of the Navy’s 2026 table for Porto do Rio de Janeiro, Ilha Fiscal (70 harmonic components, chart 1515).
05Climate
Rain and temperature, month by month.
INMET climate normals 1961–1990 for Rio de Janeiro, as the WMO World Weather Information Service publishes them.
| Month | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Year |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Rain, mm | 114 | 105 | 103 | 137 | 86 | 80 | 56 | 51 | 87 | 88 | 96 | 169 | 1,173 |
| Rain days | 12 | 9 | 9 | 10 | 8 | 6 | 6 | 6 | 9 | 10 | 11 | 13 | 109 |
| Max, °C | 29.4 | 30.2 | 29.4 | 27.8 | 26.4 | 25.2 | 25.3 | 25.6 | 25.0 | 26.0 | 27.4 | 28.6 | |
| Min, °C | 23.3 | 23.5 | 23.3 | 21.9 | 20.4 | 18.7 | 18.4 | 18.9 | 19.2 | 20.2 | 21.4 | 22.4 |
- Wettest month
- December · 169 mm
- Driest month
- August · 51 mm
- Rain days, year
- 109
- Warmest month
- February · 30.2 °C
- Coolest month
- July · 18.4 °C
Rain days count the days with at least 0.1 mm; a dash marks a month the normals leave empty.
06At this port
What the desk runs here.
Each line is coordinated from the desk in Santos, with the same procedures and the same report at every port.
- SVC-03Shipping AgencyProtective and husbandry agency with a single accountable interface, 24/7.Read more
- SVC-02Underwater ServicesHull cleaning, propeller polishing and in-water inspection by certified divers.Read more
- T-04Laytime & demurrage calculatorC/P terms and the statement of facts to laytime used, demurrage due or despatch earnedOpen the tool
- T-03Draft survey calculatorInitial and final survey to the cargo loaded or discharged: both trim corrections, density, deductiblesOpen the tool
- T-06BQS & LOP generatorThe barge’s BDN against the vessel’s soundings by ASTM Tables 54B and 56: the shortage, aeration checks and a letter of protestOpen the tool
- T-01Hold cleaning plannerStandard, laytime against the time in port, inspection risk and method for a cargo changeOpen the tool
07Quick answers
Rio de Janeiro, briefly.
What is the maximum draft at Rio de Janeiro?
Deepest berth draft: 15.30 m (TECON 1, 2, 3 and the extension, subject to the ramp-up). Source: PortosRio, Companhia Docas do Rio de Janeiro, Instrumento Normativo 14.001.08: Calados de Operação e Procedimentos Técnico-Operacionais do Porto do Rio de Janeiro.
What is the tidal range at Rio de Janeiro?
The mean range is 0.71 m, between a mean high water of 1.10 m and a mean low water of 0.39 m above chart datum, over the 1,546 high and low waters the Navy predicts for 2026 at Porto do Rio de Janeiro, Ilha Fiscal. Mean sea level stands 0.73 m above chart datum.
When is the rainy season at Rio de Janeiro?
In the INMET normals for Rio de Janeiro, December is the wettest month with 169 mm of rain and August the driest with 51 mm; the year totals 1,173 mm (normals 1961–1990). The mean daily maximum runs from 25.0 °C in September to 30.2 °C in February.
Which services does CARGOWARD run at Rio de Janeiro?
Shipping Agency · Underwater Services, coordinated by the operations desk in Santos, which answers 24/7.
08Sources
Where each figure comes from.
- [1]PortosRio, Companhia Docas do Rio de Janeiro. Instrumento Normativo 14.001.08: Calados de Operação e Procedimentos Técnico-Operacionais do Porto do Rio de Janeiro. Versão 8.0, vigente desde 10/04/2026. Read Nov 18, 2026.
- [2]Marinha do Brasil, Centro de Hidrografia da Marinha (DHN). Tábuas das Marés 2026: Porto do Rio de Janeiro, Ilha Fiscal (Estado do Rio de Janeiro). 70 componentes, nível médio 0.73 m, carta 1515. Read Nov 18, 2026.
- [3]Instituto Nacional de Meteorologia (INMET), via the World Meteorological Organization (WMO). World Weather Information Service: Rio de Janeiro, climatological information. INMET normals 1961–1990, provided to the WMO on 2004-08-02. Read Nov 18, 2026.
For planning only. Port authorities revise drafts often: the authority’s current table and the Harbour Master’s orders prevail over this page. Desk review: in progress.
Download the data