Every tonne delivered, or protested.

The barge’s BDN against the vessel’s soundings, both corrected by ASTM Tables 54B and 56: the generator finds the shortage, checks the delivery for air in the product and writes the letter of protest from the figures — a survey to share, export or send to the desk.

Output
Reconciliation · LOP · PDF
Method
ASTM D1250 · 54B · 56
Checks
Shortage · aeration · BDN
Response
< 15 min to a coordinator

Bunker quantity survey: the barge’s BDN against the vessel’s tank soundings before and after, each corrected to 15 °C by ASTM D1250 Table 54B and to metric tons in air by Table 56, the shortage against the commercial tolerance, checks for aeration, and a letter of protest written from the figures.

01

Bunkering particulars

Grade
02

BDN figures

ASTM D1250
kg/m³
°C
m³
MT
0 when the BDN gives none: the quantity is computed from its figures
Table 54B band
Fuel oils
Expansion coefficient α15
0.0006860 /°C
VCF · Table 54B
0.9810
Standard volume · m³ at 15 °C
1,030.050
WCF · Table 56
0.9843
Metric tons in air
1,013.878 MT
03

Tank soundings

Before · after

Every bunker tank that took fuel: the volume and temperature remaining on board before the delivery, then after it, from the tank tables.

Bunker tank soundings
TankROB · m³ROB · °CFinal · m³Final · °CRemove
Received per tank, at 15 °C
TankVCF · ROB / finalReceived · m³ at 15 °C
No. 1 FO tank P0.9842 / 0.9796359.306
No. 1 FO tank S0.9838 / 0.9800357.990
No. 2 FO tank C0.9855 / 0.9807294.310
Received1,032.750 m³ observed1,011.606
04

Vessel figures

Density for the vessel’s figures
Received · m³ at 15 °C
1,011.606
WCF · Table 56
0.9843
Received · MT in air
995.724 MT
Delivery temperature · from the tanks
44.7 °C
05

Delivery observations

What the vessel’s staff saw during the delivery that points to air in the product.

06

Reconciliation

Vessel − BDN

−18.154MT

−1.79 % of the BDN quantity

BDN · computed1,013.878 MT
Vessel · received995.724 MT
%
USD/MT
0 when not known
07

Forensic checks

Aeration (cappuccino) score35/100

  • Barge temperature below the one measured on board+20
  • Shortage beyond the tolerance+15
Temperature · on board less declared
+2.2 °C
What the declared temperature adds to the BDN
+1.550 MT
Loss after settling
Not re-sounded
BDN arithmetic
No stated quantity

Thresholds: temperature 2 °C to watch, 5 °C severe; settling loss 0.2 % to watch, 0.5 % severe; score 25 to watch, 50 for possible aeration.

08

Letter of protest

LOP

LETTER OF PROTEST

Ref.
LOP-CW-BQS
Place
Santos
Date
2026-11-10
To:
  • ____________, bunker supplier
  • The Master, bunker barge ____________

Subject: Short delivery of VLSFO: 18.154 MT (1.79 %) - BDN No. ____________ - M/V ____________

Dear Sirs,

Please be advised that upon completion of bunkering operations at Santos on 2026-11-10 (commenced 08:30, completed 14:10 local time), a discrepancy of 18.154 MT was found between the Vessel's measurements and the BDN figures.

The Bunker Delivery Note No. ____________ gives VLSFO 1,050.000 m³ observed at 42.5 °C with a density of 985.4 kg/m³ at 15 °C: 1,030.050 m³ at 15 °C (VCF 0.9810, ASTM D1250 Table 54B) and 1,013.878 MT in air (WCF 0.9843, Table 56).

The Vessel's soundings of her 3 bunker tanks before the delivery (the quantity remaining on board) and after it, each corrected to 15 °C at its own temperature, give 1,011.606 m³ at 15 °C received, that is 995.724 MT in air at a density of 985.4 kg/m³ at 15 °C (the BDN density).

The quantity received is therefore 18.154 MT (1.79 %) short of the BDN quantity, beyond the commercial tolerance of 0.50 %.

The temperature declared by the barge, 42.5 °C, is 2.2 °C below the temperature of the product as received on board, 44.7 °C (from the Vessel's tank temperatures). At the temperature measured on board the BDN figures give 1,012.328 MT: the declared temperature adds 1.550 MT to the BDN quantity.

We therefore hereby lodge our formal protest and hold you fully responsible for the shortage of 18.154 MT, together with all consequences, losses, delays and expenses arising therefrom. Owners and Charterers reserve all their rights in this respect, including the right to claim compensation and to have the retained samples analysed.

Samples were drawn at the Vessel's manifold throughout the delivery and sealed; they are retained on board and available for joint analysis.

We request a joint re-measurement of the barge's tanks and an immediate investigation of the matter, and ask you to acknowledge receipt of this letter.

All quantities are calculated in accordance with ASTM D1250 (Table 54B for the volume correction to 15 °C, Table 56 for the conversion to metric tons in air); the full figures are in bunker quantity survey report CW-BQS. This letter is issued without prejudice to any of the rights of the Vessel, her Owners and Charterers, all of which are expressly reserved.

Yours faithfully,

____________Master, M/V ____________
Ship’s stamp

Received for receipt only, not as acceptance of its contents:

____________Master, bunker barge ____________, for and on behalf of ____________Date and time: ____________

In English, the language of claims: a template for the Master’s signature and the ship’s stamp, to adapt to the supply contract and the charter party. Not legal advice.

09

Share

QR

Scan to open this exact survey: every figure checks against it.

Book a CARGOWARD surveyor for the next port

The figures open on an illustrative VLSFO delivery: enter the BDN’s own figures and the vessel’s soundings.

A calculation aid: the survey of record is the attending surveyor’s, on the vessel’s calibrated tank tables and the BDN.

02How to useCW-SH-02 · Rev C

BDN against soundings, one verdict.

Every correction updates as you type, and the whole survey travels in its link.

  1. 01

    Enter the BDN

    The delivery’s particulars, then the barge’s figures as the bunker delivery note gives them: the density at 15 °C, the temperature and the observed volume, and the quantity it states, if it states one.

    Go to the BDN
  2. 02

    Sound the tanks

    Every tank that took fuel, before and after the delivery: the volume and the temperature from the tank tables. Each sounding is corrected to 15 °C at its own temperature.

    Go to the soundings
  3. 03

    Read the reconciliation

    The vessel’s metric tons against the BDN’s, in tonnes and per cent, set against the commercial tolerance; the forensic checks score the signs of air in the product.

    Go to the reconciliation
  4. 04

    Issue the protest

    With a critical shortage, signs of aeration or a BDN that does not add up, the letter of protest is written from the figures: add the names and the seal numbers, and export it with the report for the Master’s signature.

    Go to the letter
03MethodCW-SH-03 · Rev C

The bunker arithmetic, step by step.

The chain a bunker surveyor runs, in the order the generator applies it.

  1. 01Table 54B · the volume correctionΔt = t − 15 °CVCF = exp(−α15 · Δt · (1 + 0.8 · α15 · Δt))

    The volume at the observed temperature brought to 15 °C. The temperature is rounded to 0.05 °C and the factor to four decimals.

  2. 02The expansion coefficientα15 = 186.9696 / ρ15² + 0.4862 / ρ15

    For fuel oils, 838.5 to 1075 kg/m³ at 15 °C. Jet fuels, the transition zone and gasolines have constants of their own in Table 54B.

  3. 03Standard volumeGSV = V × VCF

    The gross standard volume, m³ at 15 °C.

  4. 04Table 56 · weight in airWCF = (ρ15 − 1.1) / 1000MT = GSV × WCF

    The density in vacuo less the air’s buoyancy turns the standard volume into metric tons in air, the commercial figure.

  5. 05Received by the vesselReceived = Σ final − Σ ROB

    Every tank corrected at its own temperature before the sum; the tons at the BDN density, or at the vessel’s own sample.

  6. 06ReconciliationDifference = vessel − BDNPer cent = difference / BDN × 100

    Against the quantity the BDN states, or the one its own figures give; a shortage beyond the commercial tolerance is critical.

  7. 07Aeration scoreScore = Σ indicators ≤ 100

    The temperature gap, the loss after settling, the shortage and what was seen add points: 25 is to watch, 50 points to possible aeration — the cappuccino effect.

04FAQCW-SH-04 · Rev C

Questions the desk is asked most.

01What is a bunker quantity survey?

A check of the fuel a vessel receives against what the barge declares: the barge’s figures and the bunker delivery note on one side, the vessel’s tank soundings before and after on the other, both brought to the same standard by the ASTM tables.

02Why correct the volume to 15 °C?

Fuel expands as it warms: the same tonnage takes more room hot. Table 54B gives the factor that brings an observed volume to 15 °C, the reference every BDN and charter party uses, so that volumes at different temperatures compare.

03Why metric tons in air?

Fuel is bought and sold by weight in air. Table 56 takes the density in vacuo, less 1.1 kg/m³ for the air’s buoyancy, to turn the standard volume into metric tons in air.

04What is the cappuccino effect?

Air blown into the fuel during the delivery, as foam or bubbles, swells its volume: the barge’s soundings read high and the vessel pays for air. The signs: foam on the tapes and in the samples, bubbles at the sounding pipes, noise in the line, a temperature lower on the BDN than on board, and a loss of volume once the fuel settles.

05Which density should I use?

The BDN density, as a rule, so that both sides use the same figure. When the vessel’s own sample has been tested and differs, use it to see what it changes; the samples drawn at the manifold settle the question in the laboratory.

06What tolerance applies?

The one in the supply contract or the charter party. 0.5 % is a common commercial figure and the default here; within it, a difference is usually accepted as measurement uncertainty.

07When should the Master issue a letter of protest?

As soon as the difference is found, before the barge leaves and before the BDN is signed without remark: a protest made at the time keeps the owners’ and charterers’ rights. The barge master signs it for receipt only.

08Why re-sound the tanks after settling?

Air caught in the fuel escapes over the following hours. A second sounding of every tank once the product has settled shows the loss; a loss beyond a few tenths of a per cent points to aeration during the delivery.

09Is the letter of protest legal advice?

No. It is a template written from the figures, in English, the language of claims: adapt it to the supply contract and the charter party, and take advice from your P&I club or lawyer when a claim follows.

10Is the result the official figure?

It is a calculation aid. The survey of record is the attending surveyor’s, made on the vessel’s calibrated tank tables, the barge’s figures and the samples; the desk attends bunker surveys in every Brazilian port.