Laytime and Demurrage Calculation: A Worked Example

A full laytime calculation from charter party terms and a statement of facts: time allowed, exceptions, when laytime expires and the demurrage due.

Η αναφορά δημοσιεύεται στα αγγλικά· η μετάφραση θα ακολουθήσει.

Δημοσίευση
Χρόνος ανάγνωσης
6 λεπτά
Συντάκτης
CARGOWARD® Technical Desk · Chartering & Agency
Γραμμή υπηρεσίας
Ναυτική Πρακτόρευση →
Κοινοποίηση

CW-DWG-101 · Πλοίο παραβεβλημένο

A laytime calculation turns two documents into one figure: the charter party says how much time the charterers have and what does not count, and the statement of facts says what actually happened in port. Put them side by side, line by line, and you know whether the ship earned demurrage or the charterers earned despatch. This note works through one complete laytime calculation for a grain loading in Paranaguá, with every formula shown.

The terms of the example

A Supramax loads soybeans at Paranaguá under a voyage charter party. The terms that matter for laytime:

TermValue
Cargo60,000 t soybeans
Loading rate10,000 t per weather working day of 24 consecutive hours
Sundays and holidaysIncluded (SHINC)
Notice time12 hours after a valid notice of readiness, unless sooner commenced
Shifting from anchorage to berthNot to count
Breakdown of ship's gearNot to count
DemurrageUSD 22,000 per day, pro rata
DespatchHalf demurrage, on laytime saved

Laytime allowed

With a fixed rate, the laytime allowed is the cargo quantity divided by the daily rate:

EQ. 01 — Laytime allowed
L=QR×24=60,000 t10,000 t/day×24=144 hL = \frac{Q}{R} \times 24 = \frac{60{,}000\ \text{t}}{10{,}000\ \text{t/day}} \times 24 = 144\ \text{h}
Six weather working days of 24 consecutive hours.

Πού

LL
Laytime allowedh
QQ
Cargo quantity loaded (the bill of lading figure, unless the charter says otherwise)t
RR
Loading rate per weather working dayt/day

Because Sundays and holidays are included, every calendar day counts. Under SHEX terms, Sundays and holidays would be cut out of the count as well, which is where most laytime calculation disputes begin.

From the statement of facts to the time sheet

The notice of readiness was tendered at the anchorage at 08:00 on 3 August (the charter allows notice whether in berth or not). Laytime therefore starts at 20:00, after the 12-hour notice time. From there, the statement of facts is cut into periods, and each one is marked as counting or not:

—Δείξτε ένα κελί για να δείτε τον τύπο του
Time sheet
PeriodFromToHoursCountsLaytime used (h)Cumulative
Notice time after NOR03 Aug 08:0003 Aug 20:0012,000,00d 00h 00m
At anchorage, waiting for berth03 Aug 20:0004 Aug 06:0010,0110,00d 10h 00m
Shifting anchorage to berth04 Aug 06:0004 Aug 09:003,000,00d 10h 00m
At berth, loading04 Aug 09:0005 Aug 14:0029,0129,01d 15h 00m
Rain, hatches closed05 Aug 14:0005 Aug 19:305,500,01d 15h 00m
Loading05 Aug 19:3006 Aug 11:0015,5115,52d 06h 30m
Ship’s crane breakdown06 Aug 11:0006 Aug 14:003,000,02d 06h 30m
Loading06 Aug 14:0007 Aug 02:0012,0112,02d 18h 30m
Rain, hatches closed07 Aug 02:0007 Aug 06:004,000,02d 18h 30m
Loading to completion07 Aug 06:0010 Aug 16:0082,0182,06d 04h 30m
Total176,0148,56d 04h 30m
Time sheet
Point at a cell to see its formula; copy the sheet and paste it at A1 in a spreadsheet to rework it.

The ship spent 176 hours in port from notice to completion; 148.5 of them count as laytime. Notice time, the shift to the berth, the rain and the crane breakdown are taken out under the charter's terms.

How each line is decided

Waiting at anchorage counts: the charter allows notice whether in berth or not, so waiting for the berth is the charterers' time. Shifting does not count, because the charter says so; without that clause, shifting time would usually count. Rain stops the count because laytime is in weather working days: a period when the weather prevents loading is not a working period. The ship's crane stopped work through the ship's fault, and the charter excludes breakdowns of ship's gear. Each of these decisions depends on wording: change a clause and the line changes.

When laytime expires

Laytime runs out when the cumulative count reaches the 144 hours allowed. By 06:00 on 7 August, 66.5 hours have been used; the remaining 77.5 hours run out during the final loading period, at 11:30 on 10 August. From that moment the ship is on demurrage until loading is completed at 16:00.

The maxim "once on demurrage, always on demurrage" matters here: after laytime has expired, the exceptions that stopped the clock no longer do, unless the charter party expressly says they apply during demurrage too. Had it rained on the afternoon of 10 August, the ship would still have earned demurrage for those hours.

The same search, written as code — useful when a time sheet has dozens of periods:

Pythonlaytime.py
from datetime import datetime, timedelta

def expiry(periods, allowed_h):
    """periods: (start, end, counts) in order; returns when laytime runs out."""
    used = 0.0
    for start, end, counts in periods:
        hours = (end - start).total_seconds() / 3600
        if counts and used + hours >= allowed_h:
            return start + timedelta(hours=allowed_h - used)
        if counts:
            used += hours
    return None  # laytime not used up: despatch may be due

t = lambda s: datetime.strptime(s, "%d %b %Y %H:%M")
periods = [
    (t("03 Aug 2026 20:00"), t("04 Aug 2026 06:00"), True),
    (t("04 Aug 2026 06:00"), t("04 Aug 2026 09:00"), False),  # shifting
    (t("04 Aug 2026 09:00"), t("05 Aug 2026 14:00"), True),
    (t("05 Aug 2026 14:00"), t("05 Aug 2026 19:30"), False),  # rain
    (t("05 Aug 2026 19:30"), t("06 Aug 2026 11:00"), True),
    (t("06 Aug 2026 11:00"), t("06 Aug 2026 14:00"), False),  # ship's crane
    (t("06 Aug 2026 14:00"), t("07 Aug 2026 02:00"), True),
    (t("07 Aug 2026 02:00"), t("07 Aug 2026 06:00"), False),  # rain
    (t("07 Aug 2026 06:00"), t("10 Aug 2026 16:00"), True),
]
print(expiry(periods, 144))  # 2026-08-10 11:30:00

Demurrage due

Demurrage is the time on demurrage, in days, multiplied by the daily rate:

D=hdem24×rdemD = \frac{h_{\text{dem}}}{24} \times r_{\text{dem}}
—Δείξτε ένα κελί για να δείτε τον τύπο του
Demurrage
ItemValueUnit
Cargo60.000t
Loading rate10.000t per WWD
Laytime allowed144h
Laytime used (time sheet)148,5h
Time on demurrage4,5h
Demurrage rate22.000USD per day
Demurrage due4.125USD
Demurrage

Four and a half hours on demurrage at 22.000 USD/day come to 4.125,00 USD. Small, but typical: most laytime claims are decided by a handful of hours, which is why every line of the statement of facts deserves attention.

And if loading had finished early: despatch

Suppose loading had been completed at 22:00 on 9 August. From the start of laytime that is 146 hours, less the same 15.5 hours of exceptions: 130.5 hours used, and 13.5 hours of laytime saved. At half the demurrage rate (USD 11,000 per day) the charterers would earn 6.187,50 USD in despatch. Whether despatch is paid on all time saved or only on working time saved depends, again, on the charter's wording.

Reversible and averaged laytime

The example covers a single loading port. Many charters cover loading and discharging together, and two common arrangements change the arithmetic.

With reversible laytime, the time allowed for loading and discharging is one pool: the hours saved at the loading port can be used at the discharge port, and demurrage is calculated only once, on the total. The time sheets of both ports are added before laytime expiry is worked out.

With averaged laytime, the two ports are calculated separately, and the time saved at one is set off against the demurrage incurred at the other. The result is often close to reversible laytime but not identical, because despatch and demurrage rates differ and because "once on demurrage" applies port by port.

Neither arrangement applies unless the charter party says so. Where it does, run the laytime calculation for each port first, and combine the results exactly as the clause describes.

Checks before you sign a laytime calculation

  • The notice of readiness was valid when tendered, and the notice time was applied as the charter says
  • Every exception taken out of the count is written in the charter party, not only customary
  • Weather stoppages are supported by the statement of facts and, ideally, the deck log
  • Time zones and daylight saving are consistent across all documents
  • Nothing was deducted after laytime expired unless the charter keeps the exception during demurrage
  • The cargo figure used for laytime allowed matches the bill of lading or the charter's basis
SHINC
Sundays and holidays included: they count as laytime.
SHEX
Sundays and holidays excepted: they do not count, unless used, if the charter says so.
WWD
Weather working day: a working day on which the weather allows the cargo work to proceed.
Reversible laytime
Loading and discharging time added together, so time saved at one port can be used at the other.
Despatch
Money paid by the owners for laytime saved, usually half the demurrage rate.
Pro rata
In proportion: part of a day is paid as the same part of the daily rate.

Every figure above can be reproduced with your own charter party and statement of facts in the laytime calculator, which also reads an agent's SOF pasted as text. For calls in Brazilian ports, the desk's shipping agency keeps the statement of facts that the calculation depends on. The calculation starts with the notice, so it is worth reading when a notice of readiness is valid.

Πηγές

  1. Laytime Definitions for Charter Parties 2013BIMCO, CMI, FONASBA, Chamber of Shipping · 2013
  2. Laytime and demurrageThe Shipowners' Club
  3. A brief history of laytimeSkuld

Στην πράξη

T-04Υπολογιστής σταλιών και επισταλιώνΑπό τους όρους του C/P και τη δήλωση γεγονότων στις σταλίες που χρησιμοποιήθηκαν, τις επισταλίες ή το despatchΆνοιγμα εργαλείου

SVC-03 · η υπηρεσία

Ναυτική Πρακτόρευση

Εκτελωνισμός, υπηρεσίες husbandry, αρχεία σταλιών και έλεγχος εξόδων για πλοιοκτήτες και ναυλωτές, με συντονισμό τερματικών σταθμών και αρχών από ένα γραφείο που απαντά 24/7.

Αναφορές με email

Κάθε νέα αναφορά, στα εισερχόμενά σας.

Μέθοδος, αριθμοί και τεκμήρια από το κέντρο: ένα email όταν δημοσιεύεται μια αναφορά, στη γλώσσα σας, και τίποτα άλλο.

Ένα email όταν δημοσιεύεται μια αναφορά, αφού επιβεβαιώσετε τον σύνδεσμο που στέλνουμε. Διαγραφή όποτε θέλετε. Πολιτική Απορρήτου

Κέντρο επιχειρήσεων · 24/7

Ζητήστε επιχειρησιακή υποστήριξη. Το κέντρο απαντά 24/7.

Δώστε πλοίο, λιμάνι και ETA. Ένας συντονιστής — όχι τηλεφωνικό κέντρο — απαντά εντός 15 λεπτών, μέρα ή νύχτα.

Ζητήστε σχέδιο