Statement of Facts (SOF): What the Port Agent Records
What a statement of facts must record, who signs it and why each minute matters: the events, remarks and checks that turn an SOF into a laytime claim.
- Published
- Reading time
- 6 min
- Author
- CARGOWARD® Technical Desk · Chartering & Agency
- Service line
- Shipping Agency →
CW-DWG-101 · Vessel alongsideCW-RPT-08
The statement of facts is the port call written down: a chronological record, minute by minute, of what happened to the ship from arrival to sailing. It is usually drawn up by the port agent, checked against the ship's log and signed by the master and the terminal. Months later, when owners and charterers settle laytime and demurrage, the statement of facts is often the only document both sides accept — so what it says, and how it says it, decides the money.
What a statement of facts is for
Laytime calculations depend on facts that only the people in port saw: when the ship arrived at the anchorage, when the notice of readiness went out, when it rained, when the shiploader broke down. The statement of facts captures those facts while they are fresh, in a form all parties sign.
BIMCO and FONASBA publish standard forms — a general one and one for oil and chemical tankers — and many agents use their own layouts with the same content. The form matters less than the discipline: every event, with date and time, in local time, in order, with its cause.
The events a statement of facts records
| Event | Why it matters for laytime |
|---|---|
| Arrival at the anchorage or pilot station | Shows where and when the ship arrived; under a port charter it can make her an arrived ship |
| Notice of readiness tendered and accepted | Starts the notice time; the base of the whole calculation |
| Free pratique, customs and immigration clearance | Legal readiness; relevant when the NOR was tendered before them |
| Anchor aweigh, pilot on board, all fast | Shifting time to the berth, which many charters exclude |
| Hatches opened, holds inspected and passed | A failed inspection stops the count and may invalidate the NOR |
| Cargo work commenced | May start laytime early under "unless sooner commenced" |
| Each stoppage, with start, end and cause | The exceptions: rain, shore breakdown, ship's breakdown, strikes, waiting for cargo |
| Draft surveys, initial and final | Time used by surveys, and the cargo figure |
| Cargo work completed | Usually ends laytime for that port |
| Documents on board, pilot on board, sailed | Some charters run time until documents are on board |
Stoppages, remarks and protests
A stoppage entry is only useful if it says three things: when it began, when it ended, and why. "Stopped 14:00–19:30" invites an argument; "14:00–19:30 rain, hatches closed, loading suspended" settles it.
The cause matters because charter parties treat causes differently. Rain stops the clock under weather working day terms. A breakdown of the terminal's shiploader is usually the charterers' risk and keeps the clock running; a breakdown of the ship's crane is usually the owners' and stops it. Waiting for cargo, for trucks or for documents depends entirely on the wording.
When a party disagrees with an entry, it should not refuse to sign. It signs, adds "signed under protest", and states its version in the remarks. A clean signature on a wrong entry is hard to undo later.
Who signs, and when
The agent compiles the statement of facts from its own records, the ship's log and the terminal's records. A good agent drafts it as the call goes, not after the ship has sailed, and shares the draft with the master daily so that differences are settled while everyone still remembers the day. The master signs for the ship; the terminal, shippers or receivers sign for the shore side; the agent signs as compiler. Signatures should be dated, and the document should state the time zone used — Brazilian ports keep local time, and a ship on UTC can disagree with the shore by three hours on every line.
From statement of facts to time sheet
Collect the SOF and the charter party
The signed statement of facts, any protests, and the charter's laytime, NOR and exception clauses.
Check it against the ship's log
Times of NOR, all fast, commencement, stoppages and completion should agree. Resolve differences before calculating.
Cut the call into periods
Every interval from the start of laytime to completion becomes a period, each with its cause.
Apply the charter
Each period counts, does not count, or counts in part, under the charter's terms. Laytime expires when the count reaches the time allowed.
Price the result
Time beyond laytime at the demurrage rate; time saved at the despatch rate, if agreed.
The events usually arrive as plain text in an email. Laid out one event per line, with dates and times, a statement of facts like this one can be pasted straight into the laytime calculator, which reads it in English or Portuguese:
M/V __________ — Paranaguá — loading 60,000 t soybeans
03.08.2026 0800 NOR tendered at anchorage
03.08.2026 2000 Laytime commenced
04.08.2026 0600-0900 Shifting anchorage to berth
04.08.2026 0900 All fast, berth 212
04.08.2026 1030 Commenced loading
05.08.2026 1400-1930 Rain, loading suspended
06.08.2026 1100-1400 Vessel crane breakdown
07.08.2026 0200-0600 Rain, loading suspended
10.08.2026 1600 Completed loading
10.08.2026 1900 Documents on board
These are the events behind the worked laytime calculation: 148.5 hours of laytime used against 144 allowed, and four and a half hours on demurrage.
A checklist before signing the statement of facts
- Every line has a date and a time, in one stated time zone
- The notice of readiness entry shows when it was tendered, and when and by whom it was accepted
- Every stoppage has a start, an end and a cause
- Shore and ship breakdowns are named as such
- Hold inspections are recorded with their result, and any re-inspection
- Draft surveys and their times are recorded
- Times agree with the deck log and the terminal's records
- Any disagreement is written in the remarks and signed "under protest"
Local time, UTC and the three-hour trap
Most Brazilian ports keep Brasília time, UTC−03:00; ports on the Amazon keep their own. Ships often keep their logs in UTC or in the time of their last port. A statement of facts that mixes the two shifts every event by hours and can move the expiry of laytime across a stoppage. State the time zone once, at the top, and convert everything to it.
Questions about the statement of facts
Is the statement of facts the same as the time sheet?
No. The statement of facts records what happened; the time sheet (or laytime statement) applies the charter party to those facts and calculates laytime used, demurrage or despatch.
Who prepares the statement of facts?
Usually the port agent, from its own records, the ship's log and the terminal's records. The master and the terminal sign it.
What if the master disagrees with an entry?
The master signs under protest and writes the ship's version in the remarks, or issues a separate letter of protest. Refusing to sign leaves the record incomplete.
For calls in Brazilian ports, the desk's shipping agency compiles the statement of facts from the first line to the last and sends it to owners and charterers the day the ship sails.